Jefferson, Alabama
Welcome to the Progress Online Information Center developed to provide you with ongoing information about projects and
improvements to Interstate in Jefferson County, Alabama.
Project Description
Reconstruction (Grade, Drain, Pavement, ITS, Lighting) on I - 65 from I-459 to State Route 3 (U.S. 31) in Vestavia Hills.
Major Project Benefits
- More efficient transportation flow
- Smoother road surface
- Safer drive
Length: 2.34 miles
Construction Began: March 2011
Project Completed:
Project Map
Alternate Routes
- I-65 Northbound Traffic accessing U.S. 31 will be diverted along I-459 south to exit 13 and
I-459 Traffic merging onto I-65 at the Closed Ramp will need to exit I-459 at exit 13 to U.S. 31.
Construction Updates:
Dec. 8, 2011 ALDOT Seeks Minimal Impacts on
Holiday Traffic as I-65 Concrete Project Enters Final Phases
BIRMINGHAM – Work on the Alabama Department of
Transportation’s concrete pavement project on Interstate 65
will be scheduled to result in the least possible impacts
through the rest of December as holiday shopping traffic and
holiday travel increases.
City of Hoover Mayor Gary
Ivey joined State Transportation Director John Cooper today
in making the announcement in a press release from ALDOT.
The modified schedule will result in work continuing
into early 2012 rather than a final push to finish the
project by the end of December. This will avoid lane and
ramp closures at a time when local commuter and
through-traffic is extremely heavy on I-65 and on exit
ramps. In addition to a modified schedule, ALDOT plans to
suspend lane closures during the Christmas and New Year’s
travel periods.
ALDOT’s project is replacing an
aging, maintenance intensive section of I-65 from I-459 to
Highway 31. The $21 million project will provide a smoother
ride on this 2.34-mile section of I-65. The project also
includes shoulder upgrades and replacing the exit ramps. A
speed limit of 45 mph will remain in effect until the
project is completed.
--------------------------------------------
Nov. 29, 2011 Progress65 in Birmingham Reschedules Lane Shift to
Wednesday
Work continues on Interstate 65 as part of
the Alabama Department of Transportation’s concrete pavement
project in Jefferson County.
Weather permitting,
beginning Wednesday, November 30 at 9 p.m., the southbound
travel lane of I-65 will shift to the inside lane so work
can be done to reconstruct the southbound (outside) lane.
This work will consist of grading, asphalt paving and
concrete paving. Work is expected to be completed by
Thursday, December 1 at 5 a.m.
During this operation
the southbound (inside) lane will remain open as well as the
southbound contraflow lane. This will provide two southbound
travel lanes.
This $21 million project is replacing
the aging, maintenance-intensive segment of I-65 from I-459
to Highway 31/Vestavia. The project is part of ALDOT’s
Progress on Alabama Roadways campaign to preserve critical
highway infrastructure. ALDOT has branded this project
Progress65, and when completed the new concrete surface will
provide a smoother ride along one of Alabama’s busiest
interstate corridors.
This 2.34-mile concrete
pavement project is scheduled for completion around the end
of 2011. The project includes shoulder upgrades and
replacing the concrete roadway and ramps. A speed limit of
45 mph is in effect throughout the work zone.
--------------------------------------------
Nov. 22,
2011 Progress65 in Birmingham Prepares for Lane Shift
BIRMINGHAM, Ala. – Work continues on Interstate 65 as
part of the Alabama Department of Transportation’s concrete
pavement project in Jefferson County.
Weather
permitting, beginning Monday, November 28 at 9 p.m., the
southbound travel lane of I-65 will shift to the (inside)
lane so that work can be done to reconstruct the southbound
(outside) lane. This work will consist of grading, asphalt
paving and concrete paving. Work is expected to be completed
by Wednesday, November 29 at 5 a.m.
During this
operation the southbound (inside) lane will remain open as
well as the southbound contraflow lane. This will provide
two southbound travel lanes.
This $21 million
project is replacing the aging, maintenance-intensive
segment of I-65 from I-459 to Highway 31/Vestavia. The
project is part of ALDOT’s Progress on Alabama Roadways
campaign to preserve critical highway infrastructure. ALDOT
has branded this project Progress65, and when completed the
new concrete surface will provide a smoother ride along one
of Alabama’s busiest interstate corridors.
This
2.34-mile concrete pavement project is scheduled for
completion around the end of 2011. The project includes
shoulder upgrades and replacing the concrete roadway and
ramps. A speed limit of 45 mph is in effect throughout the
work zone.
--------------------------------------------
November
17, 2011 Planned Lane Closures on I-459 Northbound,
between the U.S.11 Interchange (Exit 32) in Trussville and
the I-59 Interchange (Exit 33), for Concrete Pavement
Repairs, beginning Friday night
BIRMINGHAM, Ala. –
ALDOT announces single and double lane closures on
Interstate 459 northbound from the U.S. 11 Interchange (Exit
32) in Trussville to the I-59 Interchange (Exit 33) for
concrete pavement repairs.
Weather permitting, the
lane closures will begin on Friday, November 18 at 8 p.m.
until Saturday, November 19, at 12 p.m. (noon) and again
from Saturday, November 19 at 11 p.m. until Monday, November
21 at 5 a.m.
I-459 northbound motorists bound for
I-59 northbound or I-59 southbound are encouraged to take an
alternate route by exiting I-459 northbound at the I-20
Interchange (exit 29) and then proceed west along I-20 to
the I-59 Route Interchange (Exit 130) and then reenter I-59
northbound or southbound, to further destinations, in order
to avoid traffic congestion on I-459 Northbound.
I-20
westbound motorists bound for destinations along I-59, north
of the Trussville area that would normally travel along
I-459 northbound, are encouraged to take an alternate route
by proceeding west along I-20 to the I-59 Route Interchange
(Exit 130) and then reenter I-59 northbound or southbound,
to reach further destinations.
I-20 eastbound
motorists bound for destinations along I-59, north of the
Trussville area that would normally travel along I-459
northbound, are encouraged to take an alternate route by
proceeding west along I-20 to the I-59 Route Interchange
(Exit 130) and then reenter I-59 northbound or southbound,
to reach further destinations.
Please adjust
arrival/departure times, observe work zone speed limits and
other work zone signs, and use extreme caution in this area.
ALDOT thanks motorists for their patience during this
Maintenance Operation to improve Alabama’s roadways.
For additional road closure information, visit
www.dot.state.al.us.
--------------------------------------
Nov. 9, 2011
Progress65 in Birmingham Prepares for Lane Closure
BIRMINGHAM, Ala. – Work continues on Interstate 65 as part
of the Alabama Department of Transportation’s concrete
pavement project in Jefferson County.
Weather
permitting, Friday, November 11 beginning at 9 p.m., the
southbound (inside) lane of I-65 will be closed to
reconstruct a portion of this lane. This work will consist
of grading, asphalt paving and concrete paving. Work is
expected to be completed by 5 a.m., Monday, November 14.
During this operation the southbound (outside) lane will
remain open as well as the southbound contraflow lane. This
will provide two southbound travel lanes.
This $21
million project is replacing the aging,
maintenance-intensive segment of I-65 from I-459 to
Highway 31/Vestavia. The project is part of ALDOT’s Progress
on Alabama Roadways campaign to preserve critical highway
infrastructure. ALDOT has branded this project Progress65,
and when completed the new concrete surface will provide a
smoother ride along one of Alabama’s busiest interstate
corridors.
This 2.34-mile concrete pavement project
is scheduled for completion around the end of 2011. The
project includes shoulder upgrades and replacing the
concrete roadway and ramps. A speed limit of 45 mph is in
effect throughout the work zone.
Sign up for project
update e-mails at progress65@dot.state.al.us.
The
Progress65 web site, www.progress65.com, and toll-free
project update information line, 866-888-0822, is part of
the Alabama Department of Transportation’s Progress on
Alabama Roadways campaign to keep travelers informed of
ongoing improvements to Alabama’s interstates. Other ongoing
construction includes Progress65 in Shelby County,
Progress20 in Calhoun, Cleburne, St. Clair and Talladega
counties, and Progress59 in Etowah County.
Motorist
are urged to consider using alternate routes, adjust
arrival/departure time, observe work zone speed limits and
other work zone signs, and use extreme caution in this area.
--------------------------------------
Oct.
18, 2011 ~ Rolling Roadblock on I-65 Northbound and
Southbound Blasting Operation Continues between the
I‐20/59 and I‐ 65 Interchange and Walkers Chapel Road
BIRMINGHAM – Work continues on Interstate 65 as part of
the Alabama Department of Transportation’s project to build
an interchange to connect I-65 to Corridor X in Jefferson
County.
Weather permitting, Thursday, October 20 at
1:30 p.m., blasting operations will continue on I-65
between Daniel Payne Drive (Exit 264) and Walkers Chapel
Road (Exit 267).
A rolling roadblock by Alabama State
Troopers and the City of Fultondale police will slow I-65
traffic in both directions, northbound and southbound
between the I-20/59 & I-65 Interchange (Exit 261) and
Walkers Chapel Road (Exit 267) until blasting is complete.
This will take approximately 10 minutes to complete.
In the event of inclement weather, blasting will not take
place.
Once completed, Corridor X will be an
interstate highway between Birmingham and Memphis, TN. The
scheduled completion date on the project is 2014.
A
reduced speed limit of 45 mph is in effect throughout the
work zone. Motorists are requested to consider using
alternate routes, adjust arrival/departure times, observe
work zone speed limits and other work zone signs, and use
extreme caution in this area. ALDOT thanks motorists for
their patience during this construction operation to improve
Alabama’s roadways.
For additional road closure
information, visit www.dot.state.al.us.
------------------------------------------------------------------------------
Oct. 15, 2011 ~ Progress 65 in Birmingham Traffic
Shift Ahead: ALDOT’s Progress65 Project Prepares for Traffic
Change
BIRMINGHAM, Ala. – A major change associated
with the Progess65 Concrete Pavement project will take place
next week, possibly as early as Tuesday, October 18 at 8
p.m.
Weather permitting, ALDOT will shift one lane
of southbound traffic to the northbound roadway. Opposing
traffic will be separated by a concrete barrier. Two
additional southbound (outside) lanes will be provided
comprising a total of three southbound lanes. This traffic
configuration will last approximately four weeks.
Three newly resurfaced lanes will be open for northbound
traffic.
The $21 million project is an investment to
replace the aging, maintenance intensive segment of I-65
from I-459 to U.S. Highway 31/Vestavia. The project is part
of ALDOT’s Progress on Alabama Roadways campaign to preserve
critical highway infrastructure. ALDOT has branded this
project Progress65, and when completed the new concrete
surface will provide a smoother ride along one of Alabama’s
busiest interstate corridors.
This 2.34-mile
Concrete Pavement project is scheduled for completion around
the end of 2011. The project includes shoulder upgrades and
replacing the concrete on the roadway. A speed limit of 45
mph is in effect throughout the work zone.
Sign up
for e-mail project updates at progress65@dot.state.al.us.
The Progress 65 Web site, www.progress65.com and
toll-free project update information line, 866-888-0822, is
part of the Alabama Department of Transportation’s Progress
on Alabama Roadways campaign to keep travelers informed of
the continuing progress to improve the state’s interstates.
Additional ongoing construction projects include Progress 65
in Shelby County, Progress 20 in Calhoun, Cleburne, St.
Clair and Talladega counties, and Progress 59 in Etowah
County.
Motorist are urged to consider using
alternate routes, adjust arrival/departure time, observe
work zone speed limits and other work zone signs, and use
extreme caution in this area. ALDOT thanks motorists for
their patience during this construction to improve Alabama’s
interstates.
###
MEDIA CONTACT Linda
Crockett Media & Community Relations Bureau
334-242-6963 crockettl@dot.state.al.us
------------------------------------------------------------------------------
10/7/2011 ~ Progress65: Exit to I-65 North from I-459 to
Reopen Monday
BIRMINGHAM – The entrance ramp to
Interstate 65 North from I-459 (Exit 250) is expected to
reopen Monday, October 10 at noon, weather permitting. This
planned reopening would result in completion of this work
within the eleven days originally stated.
The Exit
250 ramp was closed to allow crews to replace a barrier
wall, improve drainage structures and rebuild the ramp
itself.
This ramp closure has the potential to
impact up to 26,000 vehicles daily, more than the 15,000
impacted by the two previous closures. Like the previous two
closures, ALDOT officials will offer alternate routes and
modified traffic schedules to assist impacted drivers while
construction crews work quickly to reopen the ramp.
The ramp closure is part of the $21 million project to
replace the aging, maintenance-intensive segment of I-65
from I-459 to Highway 31/Vestavia. The project is part of
ALDOT’s Progress on Alabama Roadways campaign to preserve
critical highway infrastructure. ALDOT has branded this
project Progress65, and when completed the new concrete
surface will provide a smoother ride along one of Alabama’s
busiest interstate corridors.
This 2.34-mile concrete
pavement project is scheduled for completion around the end
of 2011. The project includes shoulder upgrades and
replacing the concrete roadway and ramps. A speed limit of
45 mph is in effect throughout the work zone.
Sign up
for project update e-mails at progress65@dot.state.al.us.
The Progress65 web site, www.progress65.com, and
toll-free project update information line, 866-888-0822, are
part of the Alabama Department of Transportation’s Progress
on Alabama Roadways campaign to keep travelers informed of
ongoing improvements to Alabama’s interstates. Other ongoing
construction includes Progress65 in Shelby County,
Progress20 in Calhoun, Cleburne, St. Clair and Talladega
counties, and Progress59 in Etowah County.
Motorist
are urged to consider using alternate routes, adjust
arrival/departure time, observe work zone speed limits and
other work zone signs, and use extreme caution in this area.
------------------------------------------------------------------------------
8/24/2011 ~ Progress65: Ramp Opening Ahead of Schedule -
Next Ramp Closure to Begin Immediately
The ramp from
U.S. Highway 31 onto Interstate 65 is expected to open
Thursday evening after being totally rebuilt as part of a
major interstate improvement project.
The ramp was
closed at 6 p.m. last Saturday for a rebuilding process that
was expected to take at least eight days. Completion in less
than eight days qualifies the contractor for a bonus that
will be calculated by ALDOT officials based on the exact
time of re-opening.
The next phase of rebuilding will
require closing the exit ramp from I-65 North to U.S.
Highway 31 (Exit 252). This off-ramp is expected to close at
approximately 6 p.m. Thursday in conjunction with opening
the adjacent ramp to I-65. Closing the Exit 252 ramp will
allow crews to replace a barrier wall, improve drainage
structures and rebuild the ramp itself. Unlike the first
ramp closure, there is no timeline for how long the work may
take but a bonus tied to the entire project will serve as
incentive to return the ramp to service as soon as possible.
Detour signs and variable message boards will help guide
traffic around the closed ramp. I-65 northbound traffic
seeking to use the closed ramp for access to U.S. 31 would
be diverted along I-459 South to Exit 13, the U.S. 31 exit.
I-459 traffic seeking to merge onto I-65 and then take the
closed ramp would instead need to exit I-459 at Exit 13 to
U.S. 31.
Additional ramp closures will be necessary
as the project moves forward.
ALDOT’s project to
replace the aging, maintenance-intensive segment of I-65
from I-459 to Highway 31/Vestavia represents a $21 million
upgrade for one of Alabama’s busiest interstate corridors.
ALDOT has branded this project Progress65.
This
2.34-mile concrete pavement project is scheduled for
completion around the end of 2011. The project includes
shoulder upgrades and replacing the concrete roadway and
ramps. A speed limit of 45 mph is in effect throughout the
work zone.
Sign up for project update e-mails at
progress65@dot.state.al.us.
The Progress65 web site,
www.progress65.com, and toll-free project update information
line, 866-888-0822, is part of the Alabama Department of
Transportation’s Progress on Alabama Roadways campaign to
keep travelers informed of ongoing improvements to Alabama’s
interstates.
Motorist are urged to consider using
alternate routes, adjust arrival/departure time, observe
work zone speed limits and other work zone signs, and use
extreme caution in this area.
------------------------------------------------------------------------------
8/18/2011 ~ Progress65 in Birmingham Prepares for First Ramp
Closure
BIRMINGHAM, Ala. – Work continues on
Interstate 65 as part of the Alabama Department of
Transportation’s concrete pavement project in Jefferson
County.
ALDOT’s contractor has reached a phase of
work that will require the ramp from U.S. Highway 31 to
Interstate 65 North to be closed for the ramp to be
completely rebuilt. Weather permitting, the ramp closure
will begin at 6 p.m. Saturday, August 20. The official
signed detour for Highway 31 to access I-65 North is to
follow Highway 31 South to I-459 North and back onto
I-65 North at Exit 250.
ALDOT estimates the ramp
closure will last for eight days. ALDOT will assess a
penalty against the contractor if the work takes longer than
eight days. The contractor could qualify for a bonus if the
work is completed in less than eight days.
Three
other entrance and exit ramp closures will be necessary as
the project moves forward. The schedule for those additional
ramp closures has not been set, but only one closure will
take place at any given time. ALDOT will announce each ramp
closure in advance.
This $21 million project is
replacing the aging, maintenance-intensive segment of I-65
from I-459 to Highway 31/Vestavia. The project is part
of ALDOT’s Progress on Alabama Roadways campaign to preserve
critical highway infrastructure. ALDOT has branded this
project Progress65, and when completed the new concrete
surface will provide a smoother ride along one of Alabama’s
busiest interstate corridors.
This 2.34-mile concrete
pavement project is scheduled for completion around the end
of 2011. The project includes shoulder upgrades and
replacing the concrete roadway and ramps. A speed limit of
45 mph is in effect throughout the work zone.
Sign up
for project update e-mails at progress65@dot.state.al.us.
The Progress65 web site, www.progress65.com, and
toll-free project update information line, 866-888-0822, is
part of the Alabama Department of Transportation’s Progress
on Alabama Roadways campaign to keep travelers informed of
ongoing improvements to Alabama’s interstates. Other ongoing
construction includes Progress65 in Shelby County,
Progress20 in Calhoun, Cleburne, St. Clair and Talladega
counties, and Progress59 in Etowah County.
Motorist
are urged to consider using alternate routes, adjust
arrival/departure time, observe work zone speed limits and
other work zone signs, and use extreme caution in this area
-------------------------------------
4/19/2011 ~
Traffic Shift Ahead: ALDOT’s Progress65 Project Prepares for
Traffic Change
The traffic shift associated with the
Progess65 Concrete Pavement project, originally planned for
Monday, April 18, has been rescheduled for Wednesday or
Thursday evening of this week contingent on soil conditions.
Visit www.progress65.com for project updates.
Weather and dry soil conditions permitting, ALDOT will shift
one lane of northbound traffic to the southbound roadway. A
concrete barrier will separate opposing traffic. Two
additional northbound (outside) lanes will be provided
comprising a total of three northbound lanes. This traffic
configuration will last approximately two months.
The $21 million project is an investment to replace the
aging, maintenance intensive segment of I-65 from I-459 to
U.S. Highway 31/Vestavia. The project is part of ALDOT’s
Progress on Alabama Roadways campaign to preserve critical
highway infrastructure. ALDOT has branded this project
Progress65, and when completed the new concrete surface will
provide a smoother ride along one of Alabama’s busiest
interstate corridors.
This 2.34-mile Concrete
Pavement project is scheduled for completion around the end
of 2011. The project includes shoulder upgrades and
replacing the concrete on the roadway. A speed limit of 45
mph is in effect throughout the work zone.
Sign up
for e-mail project updates at progress65@dot.state.al.us.
The Progress 65 Web site, www.progress65.com and
toll-free project update information line, 866-888-0822, is
part of the Alabama Department of Transportation’s Progress
on Alabama Roadways campaign to keep travelers informed of
the continuing progress to improve the state’s interstates.
Additional ongoing construction projects include Progress 65
in Shelby County, Progress 20 in Calhoun, Cleburne, St.
Clair and Talladega counties, and Progress 59 in Etowah
County.
Motorist are urged to consider using
alternate routes, adjust arrival/departure time, observe
work zone speed limits and other work zone signs, and use
extreme caution in this area. ALDOT thanks motorists for
their patience during this construction to improve Alabama’s
interstates.
-------------------------------------
3/22/2011 ~
PROGRESS 65 Announces Northbound Lane Closure Tuesday Night
Work continues on Interstate 65 as part of the Alabama
Department of Transportation’s project to rebuild the
original 30-year-old concrete roadbed on a busy 2.34-mile
segment of Interstate 65 in Jefferson County. Contractor
personnel on Tuesday, March 22 after the evening commuter
period will begin setting temporary barrier rail to close
the northbound lane of I-65 between mile markers 250 and
252. Weather permitting, work will continue around the clock
and move into the southbound lanes so that both outside
lanes will be closed by the end of the week. These outside
lane closures are necessary to provide a safe zone for
workers to upgrade the shoulders in preparation for the next
phases of work. The inside and center lanes will remain open
during this phase of work, but other lane changes will take
place in the next few weeks.
Once the shoulders are
upgraded, traffic will be shifted while rebuilding begins
first on the northbound lanes, then on the southbound lanes.
ALDOT and its contractor will make every effort to minimize
traffic impacts, but this rebuilding project will result in
lane closures and traffic shifts throughout the duration of
the project. It will also result in the use of alternate
routes while exit ramps are closed to be rebuilt. Ramp
closures will be done one at a time, ranging from a maximum
of eight to 14 days each.
--------------------------------------
3/21/2011 ~
The first traffic impact associated with ALDOT’s Progress65
rebuilding project is scheduled to begin at 9 p.m. Friday,
March 18, with the inside southbound lane being closed in
the area where I-65 South crosses over I-459. The inside
southbound lane will be closed to allow a safe zone for
workers to upgrade the shoulder in that area in anticipation
of future phases of work. The lane will re-open by 5 a.m.
Monday for the work-week commute. Other early phases of work
will result in outside shoulder upgrades on I-65 northbound
and southbound, and will require the outside lane in both
directions to be closed and blocked off by temporary
concrete barrier walls to provide a safe work zone. Those
single outside lane closures and installation of temporary
barrier wall may begin as early as Sunday, March 20. Once
the shoulders are upgraded, traffic will be shifted while
rebuilding begins first on the northbound lanes, then on the
southbound lanes. ALDOT and its contractor will make every
effort to minimize traffic impacts, but this rebuilding
project will result in lane closures and traffic shifts
throughout the duration of the project. It will also result
in the use of alternate routes while exit ramps are closed
to be rebuilt. Ramp closures will be done one at a time,
ranging from a maximum of eight to14 days each. Moderate
delays can be expected. A speed limit of 45 mph will be
strongly enforced in the Work Zone.
Expected Public Impact:
Work Zone Driving Tips
- Adhere to the posted speed limits.
- Pay Attention.
- Use proper turn signals for lane changes.
- Do not weave in and out of traffic.
- Keep a safe distance form the car ahead.
- Minimize distractions such as using cellular telephones.
- As always, buckle up.
- For your safety and the safety of others, watch for lane/ramp closures and detour signs.
- Continue to pay attention to work zone signs, even when the work is long term or widespread.
- Remain Calm.
|